31-10-2022, 07:37 PM
Noticias:
This Thursday from 00.00 to 3.00 in the morning there will be power cuts in Tuineje and Pájara.
In principle the cut for improvements in the network was scheduled for last week and has been moved to this Thursday.
Endesa informs its customers residing in the municipalities of Tuineje and Pájara, on the island of Fuerteventura, that the supply cut scheduled for Thursday, October 30, is moved to Thursday, November 3, in the range from 00.00 to 03.00 hours. This situation occurs as a result of the improvement works in the Transmission Grid that will be carried out by the Redeia group, formerly Red Eléctrica Española (REE). For this reason, Endesa warns its users of this temporary interruption and hopes that when it occurs in the early hours of the morning, the inconvenience that may be caused will be reduced.
In this sense, Redeia will temporarily leave the electrical transmission substations of Gran Tarajal 66kV and Matas Blancas 66kV without voltage to carry out repair and adaptation works of the underground section of the 66 kV Las Salinas-Gran Tarajal line on the island of Fuerteventura.
The works planned by Redeia in the transport network will mean an interruption of supply to customers and to Endesa's generation connected to the distribution network, affecting a market of some 15,519 customers residing in the municipalities of Tuineje (Tarajalejo, Valle de Tarajalejo, Marco Sánchez, Tamaretilla, Cardón, Montaña Cendida, La Calabaza, Valle de Tesejerague, Tesejerague, Los Adejes, Giniginámar, Valle de Giniginamar, Violante, Mazacote, Piedra Hincada, Diego Alonso, Finca Araña, El Polvorín, La Fuentita, El Charco, El Aceitún Gran Tarajal) and Pájara (Morro Jable, Solana Matorral, Las Gaviotas, Esquinzo, Cañada del Rio, Costa Calma, La Pared, Las Hermosas, Ugán, Tarajal de Sancho, Valle Lajita and Lajita).
This Thursday from 00.00 to 3.00 in the morning there will be power cuts in Tuineje and Pájara.
In principle the cut for improvements in the network was scheduled for last week and has been moved to this Thursday.
Endesa informs its customers residing in the municipalities of Tuineje and Pájara, on the island of Fuerteventura, that the supply cut scheduled for Thursday, October 30, is moved to Thursday, November 3, in the range from 00.00 to 03.00 hours. This situation occurs as a result of the improvement works in the Transmission Grid that will be carried out by the Redeia group, formerly Red Eléctrica Española (REE). For this reason, Endesa warns its users of this temporary interruption and hopes that when it occurs in the early hours of the morning, the inconvenience that may be caused will be reduced.
In this sense, Redeia will temporarily leave the electrical transmission substations of Gran Tarajal 66kV and Matas Blancas 66kV without voltage to carry out repair and adaptation works of the underground section of the 66 kV Las Salinas-Gran Tarajal line on the island of Fuerteventura.
The works planned by Redeia in the transport network will mean an interruption of supply to customers and to Endesa's generation connected to the distribution network, affecting a market of some 15,519 customers residing in the municipalities of Tuineje (Tarajalejo, Valle de Tarajalejo, Marco Sánchez, Tamaretilla, Cardón, Montaña Cendida, La Calabaza, Valle de Tesejerague, Tesejerague, Los Adejes, Giniginámar, Valle de Giniginamar, Violante, Mazacote, Piedra Hincada, Diego Alonso, Finca Araña, El Polvorín, La Fuentita, El Charco, El Aceitún Gran Tarajal) and Pájara (Morro Jable, Solana Matorral, Las Gaviotas, Esquinzo, Cañada del Rio, Costa Calma, La Pared, Las Hermosas, Ugán, Tarajal de Sancho, Valle Lajita and Lajita).