Roque Calero presents in Betancuria, "Purification plant of the beach of the Valley".
This morning we listened on the radio to Roque Calero, Dr. Industrial Engineer, who presented last week in Betancuria the study: 'Potabilizadora de la playa del Valle'.
Calero pointed out that the project contemplates the production of about 400,000 M3 per year for a population of 3000 people.
The budget of the project is around 11 million euros, including the pumping of water to the populated area of the municipality.
Tamara - would be nice to see similar for other towns on the west coast, El Cotillo, Tindaya etc. This would then provide redundancy against the main Corralejo and Puerto desal activities. Obviously for towns further south as well.
Roque Calero presents in Betancuria, "Purification plant of the beach of the Valley".
This morning we listened on the radio to Roque Calero, Dr. Industrial Engineer, who presented last week in Betancuria the study: 'Potabilizadora de la playa del Valle'.
Calero pointed out that the project contemplates the production of about 400,000 M3 per year for a population of 3000 people.
The budget of the project is around 11 million euros, including the pumping of water to the populated area of the municipality.