25-03-2020, 11:40 PM
I hope you are going to do regular updates Tamara so we can see the progress & the end result. It’s great all the innovations in building techniques these days 😁😁
![]() |
| house steel tindaya framed going |
|
Steel framed house going up in Tindaya
|
|
25-03-2020, 11:40 PM
I hope you are going to do regular updates Tamara so we can see the progress & the end result. It’s great all the innovations in building techniques these days 😁😁
1 user says Thank You to Spitfire58 for this post
26-03-2020, 05:35 AM
2 users say Thank You to windermeregolfer for this post
27-03-2020, 10:41 PM
Very little seemed to happen yesterday but the crane was back today lifting more sections into place. There is now another section with the sloped roof. A ceiling frame has gone in over one third - looks like they are creating a roof terrace.
3 users say Thank You to TamaraEnLaPlaya for this post
28-03-2020, 06:28 AM
(26-03-2020, 05:35 AM)windermeregolfer Wrote:(25-03-2020, 11:05 AM)Si Tie Wrote: I don't think it is temporary. I looks like aluminium box section. Sorry misunderstood. Yes my best guess they are temporary
3 users say Thank You to Si Tie for this post
21-04-2020, 12:03 AM
They started back on the build last week after a couple of weeks break. Couldn't really see any progress last week but today I could see that they have been installing what looks like a damp course:
3 users say Thank You to TamaraEnLaPlaya for this post
07-05-2020, 11:58 PM
Two steps forward and one back!
A few days ago they had the crane out and installed some pre-welded RSJs. After a couple of days the crane was back, removed the RSJs, they chopped about 1/3 of the vertical parts off and put them back in again! I think someone had got their measurements wrong . They've also been installing some boards (insulation?) above some rooms/below what looks like being a roof terrace. 02.05.20 06.05.20
5 users say Thank You to TamaraEnLaPlaya for this post
04-07-2020, 10:37 PM
Well the meccano set got completed, all the bits were found homes
![]() Now they have been attaching boards/cladding/insulation, whatever it is. The name on the product is Aquaboard. ![]() As an aside, the lorries have been driving over a piece of ground next to the site and at least once a week the mains water pipe has burst, I'm on first name terms with the guys who man the CAAF WhatsApp line
3 users say Thank You to TamaraEnLaPlaya for this post
04-07-2020, 10:43 PM
(This post was last modified: 04-07-2020, 10:44 PM by Spitfire58.)
If the drivers are bursting the water pipe on a regular basis then the companies they work for should be getting fined !!
1 user says Thank You to Spitfire58 for this post
04-07-2020, 11:29 PM
Yep, partly them and partly CAAF who are cr*p at repairs. This particular hole has had 3 repairs right next to each other in 2 weeks!
2 users say Thank You to TamaraEnLaPlaya for this post
27-07-2020, 11:22 PM
More progress over the last couple of weeks:
![]() ![]()
4 users say Thank You to TamaraEnLaPlaya for this post
|
|