The water network will be restored to 70% in a few days according to the Cabildo de Fuerteventura.
The Cabildo de Fuerteventura has announced that since yesterday afternoon, Tuesday, May 9, the fault in the impulsion network that goes from the EDAM of Puerto del Rosario to the La Herradura deposit was repaired.
According to the Water Supply Consortium of Fuerteventura (CAAF), it was necessary to wait for the drying of the fiber-cement pipe to put it back into operation.
In that sense, from today at 7:15 am the GRP DN400 pipe is being loaded and it is calculated between 4 and 5 hours, approximately, to complete the load of the impulsion pipe. Around noon the pumping will be restored, so the water will reach the regulating header tanks of La Herradura. Thus, according to what was transferred, in one or two days, the water network will be restored to 70% in many areas and the supply will return to normal.
President Lloret thanked the effort made by the CAAF for the rapid repair of the fourth fault in a month. He also thanked them for acting quickly and diligently to fix this new fault in one of the two main arteries of the supply network as soon as possible.
Also, to reinforce the supply, since yesterday the service was activated in vats in several areas, such as Tesejerague, El Cardón and the area of cattle ranchers in the south; Ampuyenta, Betancuria and the Santa Inés Valley in the center, and Tindaya in the north.
The CAAF has regretted the inconvenience caused and apologizes to users.
The water network will be restored to 70% in a few days according to the Cabildo de Fuerteventura.
The Cabildo de Fuerteventura has announced that since yesterday afternoon, Tuesday, May 9, the fault in the impulsion network that goes from the EDAM of Puerto del Rosario to the La Herradura deposit was repaired.
According to the Water Supply Consortium of Fuerteventura (CAAF), it was necessary to wait for the drying of the fiber-cement pipe to put it back into operation.
In that sense, from today at 7:15 am the GRP DN400 pipe is being loaded and it is calculated between 4 and 5 hours, approximately, to complete the load of the impulsion pipe. Around noon the pumping will be restored, so the water will reach the regulating header tanks of La Herradura. Thus, according to what was transferred, in one or two days, the water network will be restored to 70% in many areas and the supply will return to normal.
President Lloret thanked the effort made by the CAAF for the rapid repair of the fourth fault in a month. He also thanked them for acting quickly and diligently to fix this new fault in one of the two main arteries of the supply network as soon as possible.
Also, to reinforce the supply, since yesterday the service was activated in vats in several areas, such as Tesejerague, El Cardón and the area of cattle ranchers in the south; Ampuyenta, Betancuria and the Santa Inés Valley in the center, and Tindaya in the north.
The CAAF has regretted the inconvenience caused and apologizes to users.