This Fuerteventura forum uses cookies
This Fuerteventura forum makes use of cookies to store your login information if you are registered, and your last visit if you are not. Cookies are small text documents stored on your computer; the cookies set by this Fuerteventura forum can only be used on this website and pose no security risk. Cookies on this Fuerteventura forum also track the specific topics you have read and when you last read them. Please confirm whether you accept or reject these cookies being set.

A cookie will be stored in your browser regardless of choice to prevent you being asked this question again. You will be able to change your cookie settings at any time using the link in the footer.
Hi guest and welcome to the Fuerteventura forum.

Thread Rating:
  • 0 Vote(s) - 0 Average
  • 1
  • 2
  • 3
  • 4
  • 5

[-]
Tags
time someone caaf water fired

No water - it's time CAAF fired someone!
And still not a drop 😭
1 user says Thank You to TamaraEnLaPlaya for this post
Reply Quote
Water came back on this evening thank goodness. I didn't receive a reply to my email to CAAF - I'll be following that up tomorrow.

Big, big thanks to one of our forum members who offered me the opportunity to go to her house for a shower - I didn't need to take it up as our situation is being resolved but it meant so much - thankyou xx
1 user says Thank You to TamaraEnLaPlaya for this post
Reply Quote
Radio Sintonia:

The CAAF executes repair works for the improvement of the facilities.

The Fuerteventura Water Supply Consortium (CAAF) carries out maintenance work on the Puerto del Rosario distribution network from today until early in the morning.



The CAAF reports that it is a necessary repair to improve the facilities, given the persistence of incidents in this network, on which some areas of the capital of Majorera depend.



To carry out the tasks, a supply cut has been carried out, with the normality of the water supply expected to be recovered throughout today, June 27. For this reason, the CAAF apologizes to users for the inconvenience caused.
1 user says Thank You to TamaraEnLaPlaya for this post
Reply Quote
Radio Sintonia:

The CAAF will carry out preventive maintenance work in the EDAM of Puerto del Rosario.

The Fuerteventura Water Supply Consortium (CAAF) will undertake maintenance work at the desalination plant in Puerto del Rosario. It is about executing preventive maintenance tasks of one of the modules of this plant, so the flow of contribution to the deposits located in La Herradura will be reduced by 7,000 m3 / day.





Preventive maintenance in the face of expected summer consumption
The work is scheduled for next Tuesday. July 4. They will begin early in the morning and the work is expected to be completed around 16:00 p.m.

These preventive maintenance works in the Puerto del Rosario EDAM are necessary due to the proximity of the summer season, in which a higher consumption than usual is expected, in addition to expected temperature rises.

From the CAAF it is also reported that it is a necessary repair to improve efficiency and increase production in facilities that present a remarkable fragility due to their obsolescence.

Normality in the water supply is expected to return during the same Tuesday. For this reason, the CAAF apologizes to users.
2 users say Thank You to TamaraEnLaPlaya for this post
Reply Quote
Radio Sintonia:

Solved a fault in one of the sides of the Las Rotondas Shopping Center, on Pi and Arsuaga Street.

Operators of the Services area of the City Council of Puerto del Rosario repair since Monday morning a fault in a water pipe that caused the collapse of a sidewalk on one of the sides of the Las Rotondas Shopping Center, on Pi and Arsuaga streets.







A breakdown in which we work together with the Consortium of Water Supply to Fuerteventura (CAAF), with the aim of solving it as quickly as possible and returning normality to this street through which many pedestrians and drivers travel daily, who go to make their purchases to this commercial area of the capital.



The mayor of Puerto del Rosario, David de Vera, asked for patience to the neighbors for the inconveniences that the works may cause, he also recalled that "the objective of the City Council is to make the necessary improvements to renew the water supply network and prevent new breakdowns from occurring. "



For his part, the Councilor of Aguas del Cabildo, Adargoma Hernández, stressed the importance of "there is continuous communication between the CAAF and the different municipalities of the Island when addressing this type of breakdown, as well as close cooperation to renew the networks as the different municipal works are carried out. "



From the City Council of Puerto del Rosario and the CAAF, pedestrians and drivers are requested to travel through the affected area with caution and attend to road signs.
1 user says Thank You to TamaraEnLaPlaya for this post
Reply Quote
Noticias:

4.6 km of pipes to carry water to the La Herradura reservoir.

The manufacturer of Fiberglass Reinforced Polyester (GRP) pipes and fittings Amiblu has completed the supply of 4.6 km of GRP pipes for the drinking water supply work from the Puerto del Rosario desalination plant to the La Herradura tanks.



The total length of the pipeline supplied by Amiblu in Fuerteventura is 4,686 meters of GRP tubes with diameter DN800 in pressures of 10, 16 and 25 bars, with multiple accessories of all kinds, such as flanges, elbows, tes, etc. The main challenges have been the realization of a profile that minimizes the angles of the route of the pipe, the underground passages by gallery – having to use anchors for the placement of the pipe in aerial – and the placement of a collector piece located in an area with multiple services affected and that is in the manufacturing phase.



The execution of this work is of vital importance for the island, as it guarantees the supply of drinking water. In fact, it has been completely necessary in light of the frequent breakdowns that the existing impulsion pipes had been suffering, the result of their poor condition after more than 30 years in use.



The project is part of the 'Insular Cooperation Plan for the guarantee of domestic water supply Isla de Fuerteventura' (PICABAS 2020-2025) of the Ministry of Infrastructure of the Cabildo de Fuerteventura, through the Water Supply Consortium of Fuerteventura (CAAF), for the impulsion of drinking water from the Production Center of Puerto del Rosario (EDAM Puerto del Rosario) to the regulatory deposits of La Herradura.It has a total budget of 3.2 million of euros.



Energy efficiency of GRP pipes



GRP pipes offer significant advantages for the supply of drinking water, compared to pipes made of traditional materials, such as concrete or steel. With a very durable service life, they stand out for having a smooth inner surface, as well as for their excellent hydraulic properties, with significantly low friction losses. In addition, they are more environmentally friendly – they have a CO2 impact three times lower – lighter, easier to transport and handle, and more energy efficient.
2 users say Thank You to TamaraEnLaPlaya for this post
Reply Quote
Radio Sintonia:

The area of Costa Antigua will suffer water cuts this Wednesday.

The Antigua Water Mixed Company informs that a maintenance action will be carried out on the General Supply Network in the Costa Antigua sector (Nuevo Horizonte), Caleta de Fuste, which will cause supply cuts at the time of the action. It will run between 8:00 a.m. and 14:00 p.m. on Wednesday, July 19.



However, the company assures that the works will be executed as soon as possible, causing the least inconvenience to neighbors, users and businesses in the area. Once the intervention is over, they declare that "the supply service will be substantially improved".
2 users say Thank You to TamaraEnLaPlaya for this post
Reply Quote
Radio Sintonia:

The CAAF communicates a scheduled supply cut.

The General Directorate of Roads has requested a scheduled cut that will take place tomorrow Thursday and could affect users from Risco Prieto to Llanos de La Mareta



The Fuerteventura Water Supply Consortium (CAAF) wishes to inform the community that a scheduled supply cut will be carried out due to the construction works of the section of the Puerto del Rosario-La Caldereta highway. This cut will affect the water supply in the area of Playa Blanca (Puerto del Rosario).

The works require diverting one of the main pipes, specifically the pipe that supplies drinking water from the industrial estate of Risco Prieto to Llanos de La Mareta.

For this reason, the General Directorate of Roads of the Government of the Canary Islands, responsible for the works, has requested the CAAF a scheduled cut. It will take place tomorrow, Thursday, July 20, from 08.00 to 14.00.

The CAAF apologizes for the inconvenience that this cut may cause to users of the areas of Risco Prieto, Las Granadas urbanization, Playa Blanca, Airport, El Matorral and Llanos de La Mareta.
1 user says Thank You to TamaraEnLaPlaya for this post
Reply Quote
Radio Sintonia:

The CAAF repairs an incident in the desalination plant of Puerto del Rosario.

The Fuerteventura Water Supply Consortium repairs a fault in one of the sea catchment pumps of the Puerto del Rosario desalination plant. An incident that involves a loss of production of 240 cubic meters / hour, which leads to a reduction in flow in the networks that will affect Fuerteventura in general.



The CAAF has immediately activated the action protocol, hoping to resolve the incident and restore the supply normally in the shortest possible time. At the same time, it apologizes to users for the inconvenience caused.
3 users say Thank You to TamaraEnLaPlaya for this post
Reply Quote
Forgive me if I am being lazy Tamara, but what is the best/easiest way to contact CAAF if we see a leak?
Reply Quote


Possibly Related Threads...
Thread Author Replies Views Last Post
  Water suppliers: CAAF & bills? Ducks 16 6,278 06-07-2026, 12:31 PM
Last Post: Kmfoznuuz
  CAAF hotline for leaks Bill 0 1,940 23-05-2024, 05:43 PM
Last Post: Bill
  Warning! E Coli in CAAF water Emmi Smith 2 6,311 11-07-2020, 06:47 PM
Last Post: Lexeus